F3 Field Service Manual
Page 16
Figure 12: Correct Fitting of the Wiring Loom into the Electronics Pack
NOTE
Take great care when connecting the wiring loom plug to the electronics pack. DO NOT
force the connection because this could damage or break the connector on the printed
circuit board.
Fold excess wiring loom cable into the electronics pack above the plug.
Figure 13: Excess Wiring Loom Cable Folded Correctly & Cable Router
Refit the bulkhead cover with six screws.
Route the wiring loom around the cable router on the side of the bulkhead cover.
(Figure 13)
Refit the sensitivity endcap.